Project Updates

March 1, 2016

Studies and Status

  • Topographical Survey, Geotech Studies, LNG Storage Study,Vaporizer Selection Study
  • Seismic Hazard Study, Marine Due DiligenceRegulatory Compliance Study
  • Front End Engineering & Design (FEED)FEED Review
  • CRZ Clearance and Environmental Clearance received
  • Gas Market Study
  • Simulation Model for Terminal Operations
  • Marine HAZID, HAZOP, gas plume etc.
  • Risk studies (HAZID, HAZOP, RAM, QRA)
  • Logistics Study & Detailed Project Report
  • Advanced stages of discussion with customers for capacity booking
  • EPC Contract awarded to Awarded to Sener – Afcons

    Milestones

Schedule Timeline
Start of site preparation Completed
EC, CRZ and other Critical Received
EPC Contract Awarded
Mechanical complletion of LNG Terminal Q2 – 2019
Commissioning & Start up Q3 – 2019
Commercial Operations Q4 – 2019